SITE FORMATION
- 2018-Current
- BACHY SOLETANCHE GROUP LTD.Hong Kong International Airport 3503 - Terminal 2
Foundation and Substructure Works Construction of Concrete Slab
Diaphragm Wall and Guide Wall Construction
Soil Disposal
- 2018-2019
- MTR CORPORATION LIMITEDExpress Rail Link Contract 8209
Design and construction of Nam Cheong Park Reinstatement
- 2016-2018
- VINCI CONSTRUCTION GRANDS PROJETSMTR Corporation Ltd. SCL1122
Admiralty South Overrun Tunnel Mucking Out Subcontract
- 2016-2018
- MTR CORPORATION LIMITEDMTR Corporation Ltd. XRL8217
Shek Yam Backfilling of Shek Yam Construction Adit
Reinstatement Work
Reinstate the existing stone wall
Hydroseeding work
- 2014-Current
- DRAGAGES-BOUYGUES JVMTR Corporation Ltd. SCL1128
South Ventilation Building to Admiralty Tunnels Excavation and Lateral Support for W1 Advanced Shaft
Construction of Concrete Slab and Reinstatement Works at Wan Chai Sports Ground
Noise Cover and Enclosure at Works Area W1 Advanced Shaft
Excavation of FPP Peanut Shaft at Works Area W8
Disposal of Spoil Excavated from TBM Tunnels
Excavation of SOV Shaft at Works Area W2
Demolition of Perimeter Wall at Works Area W14
Earthwork and R.C. Works at FPP Area 2 Shaft at Works Area W8
Demolition of Slurry Treatment Plant (Reinforced Concrete Structure)
Disposal of Precast Concrete Segments from Works area W21 to Tuen Mun River Trade Terminal
Disposal of the Demolished Temporary Concrete Structures in East Tunnels at Works Area W1/W2
Removal of Concrete Slab for POC’s Pre-Bored H-Piles Construction at Works Area W2
Construction of Fenwick Pier Emergency Egress Point and Cut & Cover Tunnel at Works Area W8
Demolition of Slurry Treatment Plant (Reinforced Concrete Structure) Works Area W14
- 2014-Current
- DRAGAGES HONG KONG LTD.Civil Eng. and Development Department CV/2012/08
Liantang / Heung Yuen Wai Boundary Control Point
Site Formation and Infrastructure Works - Contract 2 Earthwork at North Portal
Site Formation, Slope and Drainage Works at Mid Ventilation Adit Portal
Platform Formation for Bridge Construction at South Portal
Sedimentation Tank at Mid Ventilation Portal
Disposal of Excavated Material from Adit at Mid Ventilation Portal
Site Formation, Slope and Drainage Works at South Portal
ELS at Spoil Basin at North Portal
Disposal of Excavated Material from Tunnels at North Portal
Disposal of Excavation Materials from Drill and Blast Tunnel at South Portal
Earthwork for Administration Building
Additional Works for Spoil Basin ELS
Earthwork for Administration Building Foundation
Shotcreting works for TBM Tunnels
Material Handling for TBM Tunnels
Permanent Soil Nailing Works at North Portal
- 2013-2018
- VINCI CONSTRUCTION GRANDS PROJETSMTR Corporation Ltd. SCL1103
Hin Keng to Diamond Hill Tunnels Construction for MCV Temporary Platform
Construction for FTA Temporary Platform
Mucking Outs Works
Excavation at Mucking Out at Portal at Hin Keng
Hin Keng Box 2 Excavation
Shaft Excavation at Diamond Hill Site
To supply and install Cut-off Wall Capping Beam at Diamond Hill Station
DIH Capping Beam Remaining D-wall Panels
Construction of Base Slab at Diamond Hill Station
Rock Filling and Concrete Slab at Shui Chuen O
Shaft & Central Accomodation Excavation & ELS Works at Ma Chai Hang
Excavation of Cut and Cover Tunnel Area 3 at Hin Keng
Site Clearance of TKO Magazine
Concrete Structure Breaking and Excavation for DIH Site Area
Demolition and Removal of 3rd Filter Structure at DIH site
Reinstatement Works at Hin Keng and W5B
- 2012-2015
- NISHIMATSU CONSTRUCTION CO., LTD.MTR Corporation Ltd. SIL902
Nam Fung Tunnel and Ventilation Buildings Land & Marine Disposal and Barging Point Operation
- 2012-2014
- LEIGHTON-GAMMON JVMTR Corporation Ltd. XRL810A
West Kowloon Terminus Station North Sorting and Disposal of Excavated Rock Material to XRL821
- 2012-2013
- LEIGHTON CONTRACTORS (ASIA) LTD.MTR Corporation Ltd. XRL822
Tse Uk Tsuen to Shek Yam Tunnels Tunnel Spoil Disposal
- 2012-2013
- BACHY SOLETANCHE GROUP LTD.CB204
Proposed Goldin Financial Global Centre at NKIL 6314 Kln. Spoil Removal for Diaphragm Wall, Bored Piles and Socketed H-Piles
- 2011-2018
- LAING O'ROURKE-HSIN CHONG-PAUL Y JVMTR Corporation Ltd. XRL810B
West Kowloon Terminus Station Basement Ventilation for top down construction
Supply and Installation of General Fill and Sub-base Material to Ground Floor Slab
Barging Point Reinstatement Works
- 2011-2011
- BACHY SOLETANCHE GROUP LTD.Drainage Services Department DC/2007/24
Harbour Treatment Scheme
Shear pins construction at Sai Ying Pun
- 2010-2016
- DRAGAGES-BOUYGUES JVMTR Corporation Ltd. XRL820
Mei Lai Road to Hoi Ting Road Tunnels Construction of Sheet Piling Wall for DSD Rising Main Diversion
Construction of Socketed H-Pile
Foundation for DSD Rising Main Diversion
Construction of Temporary Fill Platform at Nam Cheong Launching Shaft
Site Establishment Works at Nam Cheong Barging Point
Construction of Concrete Slab inside Slurry Treatment Tanks
Construction of Slurry Tank Foundation Slab
Construction of Filter Press Slab for Slurry treatment plant
Additional Works for Backfilling of Retrieval Shaft 811A
Dismantling & Removal of Container Surrounding Site 6 Stockpile
Miscellaneous Works for Rockfill Layer at Nam Cheong Launching Shaft
- 2010-2015
- DRAGAGES-BOUYGUES JVMTR Corporation Ltd. XRL821
Shek Yam to Mei Lai Road Tunnels Land Transportation of De-sanding Materials
Earthwork, Concrete Work and Miscellaneous
Breaking out of Concrete Invert Slab inside Tunnel Work for VB6
Closure of openings in 821 Twin Track Tunnel
Remedial works inside the Tunnels due to setting out errors
Backfilling to North & South Adit Bypasses
- 2010-2013
- BACHY SOLETANCHE-LAING O'ROURKE JVMTR Corporation Ltd. XRL811A
West Kowloon Terminus Approach Tunnel Site Clearance and Construction of Temporary Carriageway and
Spoil Disposal for Piled Foundations Excavation & Lateral Support (ELS)
- 2010-2011
- BACHY SOLETANCHE GROUP LTD.MTR Corporation Ltd. XRL825
Mai Po to Ngau Tam Mei Tunnels Spoil Removal, Guide Walls
- 2009-2010
- BACHY SOLETANCHE GROUP LTD.Proposed Development at TPTL No.188 Pak Shek Kok, Tai Po
Guide Wall and Spoil disposal
- 2008-2013
- DRAGAGES-NISHIMATSU JVDrainage Services Department DC/2007/10
Design and Construction of Hong Kong West Drainage Tunnel Earthworks and Reinforced Concrete Works of Spoil Bsin at Western Portal
Excavated Materials Off Site from Western Portal
Supply of Pea Gravel to Western Portal
Site Set Up, Temporary Drainage Works, Shaft Intake & Slope works at Intake TP4, TP5, TP789
Temporary excavation and lateral supporting for deep structures
Removal of Pipe Pipes
- 2008-2009
- BACHY SOLETANCHE GROUP LTD.Contract for Foundation Works
Cathay Pacific Air Cargo Shoring installation
Spoil removal, pile head trimming & sheet pile
- 2005-2006
- BACHY SOLETANCHE GROUP LTD.Contract No. C407D
Tung Chung Station Development
Package 2, Phase 4 Lowrise Development Removal of Spoil & Construction of Guide Wall
Installation of sheet piling work
Construction of foundation work.
- 2004-2005
- BACHY SOLETANCHE GROUP LTD.Contract P352
Skyplaza Advance Works Construction of Guide Wall and Removal of Rock Fill
- 2003-2006
- VSL HONG KONG LTD.Contract No. HY/99/19
Castle Peak Road Castle Peak Road Improvement
Construction of Reinforced Earth Wall
- 2003-2004
- BACHY SOLETANCHE GROUP LTD.Contract CA211
Shek Lei Estate Phase 10 Foundation Works for Block No.11 & 12 and Car Park
for Redevelopment of Shek Lei Estate Phase 10
- 2002-2004
- CHINA STATE CONSTRUCTIONCED CV/2001/10 Contract 2 for
Infrastructures at Penny’s Bay Development Earthwork (Slope & Ground Treatment)
- 1998-1999
- KUMAGAI GUMIDiscovery Bay North Development
Tunnel Excavation Works and pipe piling work
- 1997-2000
- LEIGHTON-KUMAGAI JVAqueducts Between Tai Po
and Butterfly Valley Shing Mun Shaft Construction work including installation of sheet piling work
Excavation to Adit Tunnel and Tunnel Works Between
Tai Po Tau and Butterfly Valley including pipe piling work
- 1988-1989
- PILECONTuen Mun Private Development
TMTL292 Foundation Works for 4 Residential Towers